CITY OF OCONTO FALLS: FLATLEY AVE Construction update

Sewer

City Of Oconto Falls issued the following announcement on June 10.

Important bullet points from S. Flatley reconstruction informational meeting held on June 9, 2021: 

  • Start date, July 5, 2021
  • Estimated completion date, September 17, 2021
  • Timeline:  starting with sanitary, then water main, laterals, storm sewers.  Curb, gutter & hard service to follow, then landscaping
  • Mailbox setup will be on the South end of Sheridan
  • There will be 2 layers of asphalt due to heavy truck traffic to old dump
  • Construction is from Green bay Ave to Sheridan on S. Flatley
  • Starting North to South
  • Construction updates will be posted on the City & Utility websites
If it remains very dry during construction it was confirmed that dust control will be addressed.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS