City Of Oconto Falls issued the following announcement on June 10.
Important bullet points from S. Flatley reconstruction informational meeting held on June 9, 2021:
- Start date, July 5, 2021
- Estimated completion date, September 17, 2021
- Timeline: starting with sanitary, then water main, laterals, storm sewers. Curb, gutter & hard service to follow, then landscaping
- Mailbox setup will be on the South end of Sheridan
- There will be 2 layers of asphalt due to heavy truck traffic to old dump
- Construction is from Green bay Ave to Sheridan on S. Flatley
- Starting North to South
- Construction updates will be posted on the City & Utility websites