Quantcast

Green Bay Reporter

Saturday, November 23, 2024

ALLOUEZ VILLAGE CLERK BROWN COUNTY WI: 2020 Reconstruction Project Update (October 9, 2020)

Streetcon

Allouez Village Clerk Brown County WI issued the following on Oct. 9

This 2020 construction season has begun in The Village of Allouez, some or all of the Public Works Projects are listed below:

1. St Mary’s Boulevard — Riverside Dr to ± 1500 feet to east (#310/#311)

2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)

3. Garland Street – Webster Ave to Baird St

4. Allouez Terrace Alley – Riverside Dr to end.

5. East St Joseph Alley – behind Associated Bank

6. Olde River Condominium Trail

7. Longview Pond Trail Repair

8. Bethel Pond Project

9. Standpipe (Water Tower) Repair Project

These street improvements include:

– Removal and replacement of the asphalt pavement.

– Replacement of defective gravel base

– Replacement of defective concrete curb & gutter and driveway aprons

– Manhole & catch basin repairs

– Sanitary sewer repairs on St Mary’s Blvd

1. St Mary’s Boulevard – Riverside Dr to ± 1500 feet to east (#310/#311)

• Work started – May 7

• Completion Date – October 30th, 2020

Project Status:

Paving completed Thursday Oct 8, turf restoration of the sanitary lateral replacements to follow. General contractor & village to monitor the progress of the restored landscaping.

2. Stanton Court/Arbor Lane — Stanton Ct to Rosemont Dr (near Webster Ave)

• Work started – May 13

• Worked completed – June 26

Project Status:

Paving completed; contractor & village to monitor the progress of the restored landscaping.

3. Garland Street – Webster Ave to Baird St

• Work started – May 28

• Worked completed – June 26

Project Status:

Paving completed; contractor & village to monitor the progress of the restored landscaping.

4. Allouez Terrace Alley – Riverside Dr to end.

• Work started – May 14

• Worked completed – June 16

Project Status:

Paving completed contractor will return to install gravel shoulder.

5. East St Joseph Alley behind Associated Bank

• Work started – May 14 (asphalt removal)

• Worked completed – June 16

Project Status:

Paving completed.

**6. Olde River Condominium Trail

• Worked completed – June 16

Project Status:

Paving & shouldering completed and turf restoration started. General contractor & village to monitor the progress of the restored landscaping.

**7. Longview Pond Trail Repair

• Worked completed – June 15

Village and general contractor are monitoring the current condition of the repaired trail and future repairs are likely.

**8. Bethel Pond Project

• Work to Started – August 3

• Substantial Completion Date – October 23rd, 2020

The Village is constructing a 1-acre regional stormwater pond located east of the Bethel Baptist Church on the south side of Kalb Street. In conjunction with the project, the Village will be installing 1350 ft of 48” Storm Sewer along the south southside of Kalb Street from Irwin Avenue east to the pond.

Project Status:

The excavation of the pond is near completion and restoration of the pond area will follow. Dorner Inc is in the process of installing the 48”sewer pipe from the pond towards the west ending at Irwin St. They are through the intersection of Libal St and Kalb St and will now be working behind the curb and sidewalk in the park.

9. Standpipe (Water Tower) Repair Project

Minor structural repairs to the Water Tower are anticipated to begin on the 13th of July. In general the interior and exterior repairs consist of replacement of the overflow weir box, exterior power washing, touch-up painting, improvements to the fall protection equipment, and upgrading at grade overflow pipe.

The anticipated project schedule is as follows:

• Work Started Mid – July

• Worked Completed – August 6

Project Status:

Work has been completed and we are back to normal operations.

Original source can be found here

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS